DELIVERY OF THE HULL

ARRIVAL

Just after 9 a.m. on 10th July 2002 the hull arrived at Weltonfield by lorry, and I was waiting to see this rather exciting event!

Weltonfield Narrowboats are at Welton Hythe on the A5 about one mile south of the Watford Gap (M1) service area.

arrival by lorry

THE CRANE

The crane arrived at the same time as the boat.

crane arrival

READY TO LIFT

The lorry reversed to the water's edge ready for lifting straps to be attached.

ready to offload

LIFTING

Lifting off the lorry provided a moment of anxiety. Were the straps in the right position to balance the boat? Were the straps strong enough? Would the weight of the boat topple the crane?

But these guys were professionals. The crane driver told me the weight was only 11.1 tons - no problem!

lifting

FLOATING

Finally my boat was floating in the water! It didn't roll over and it didn't sink!

in the water

You may wish to send comments or queries to Alastair: Please click on the links below to view details and images.

[ Home Page ]   [ Introduction ]   [ Drawings ]   [ Hull ]   [ Delivery ]   [ Fitting Out 1 ]   [ Fitting Out 2 ]   [ Fitting Out 3 ]

[ Fitting Out 4 ] [ Paintwork ] [ The Relaunch ] [ The Finished Job ] [ Thumbs ] [ Detailed Spec ] [ Latest Mods ]

[ Re-blacking ] [ External Links ]